The project has been designed by City of Sand Springs Engineering Division. The project will be constructed by McGuire Brothers Construction, Inc. with Construction Administration and Inspection by ODOT, Division VIII, Sand Springs Residency.
Traffic control should begin to be put in place on this Wednesday, July 10, 2013. Traffic control will maintain at least one lane of traffic open in both directions throughout the project with the plan being to alternate lane closures to allow work to be done on both inside lanes, or both outside lanes at any stage of work.
The project has a 30 calendar day duration.